State, city agree to begin roundabout design at Deal St. and Highway 196
road work

As work on Deal Street progresses, Hinesville City Council has agreed to a framework agreement with the state Department of Transportation for a roundabout at Deal Street’s connection to Highway 196.

With those agreements, the city can ask for requests for qualifications from engineering firms, city engineer Paul Simonton said.

The design will take two to three years before construction begins, he said.

“It is a very, very thorough process,” Simonton said. “It is very, very time-consuming, with the reviews and everything.”

As an example, the widening of Veterans Parkway, from Highway 196 to Fort Stewart’s Gate 8, or Barkley Gate, took five years, including utility relocations.

Simonton noted that former city manager Kenneth Howard’s plea to enable the city’s public works vehicles to turn left onto Highway 196.

“There were a couple of alternatives,” Simonton said. “Mr. Howard said, ‘hey, I’ve got to let my people turn left coming out of public works,’ and the only way that could happen is with the roundabout.”

Work on the roundabout at the other end of Deal Street, at its intersection with South Main Street, is expected to be done in the next couple of months, Simonton said. He added they also are looking at the best way to widen Deal Street so that it ties in with the proposed roundabout at Highway 196 and with the planned event center.

The city agreed to provide approximately $110,000 of the total cost of just shy of $582,000 needed for the preliminary engineering and design. More than $440,000 of that will come from grant funds. The city is reallocating money previously set aside for sidewalk projects to the roundabout engineering and design.

The total cost for the roundabout at Deal Street and Highway 196 is projected to be about $5.9 million.